DARKMATTER RESEARCH DOSSIER • 19 OCTOBER 2026

JANUS PROGRAM

U.S. Army microreactor deployment readiness and Project Pele context. A human-readable, indexed, source-linked research website.

01 / Executive overview

Reporting cutoff: October 19, 2026. The five initial Army Janus installations have named developers, but a selected developer is not the same as an approved reactor site or operating license. This dossier separates publicly reported progress from unverified or outstanding approvals.

5Initial Army installations
$2.2BReported FY2027–31 ceiling
20+Longer-term reactor goal
30 SEP 2028Executive-order target

Evidence labels: Confirmed means the cited source describes a completed action; Reported target is not an authorization or guarantee; Not verified means this dossier does not establish completion, not that no internal work has occurred.

02 / Deployment readiness matrix

InstallationDeveloper / systemSitingRegulatoryFuelTestingConstruction / operation
Fort Benning, GARadiant / KaleidosPreferred candidate inspected Oct. 16 [S4]Final approval pendingHALEU and TRISO arrangements reportedPrototype testing preparations reportedNo verified site construction; 2028 target
Fort Bragg, NCAntares / R1Installation selected; parcel unverifiedSite approval unverifiedTRISO supply contractedMark-0 criticality, June 2026No verified site construction; 2028 deployment target
Fort Campbell, KYBWXT / BANRFinal site selection in Phase 1Regulatory process being initiatedTRISO fabrication workstreamPele provides related experience, not BANR validationLate-2028 groundbreaking target; early-2030s operation
Fort Hood, TXGeneral Atomics / GA-TESInstallation selected; parcel unverifiedApproval unverifiedSite-specific delivery unverifiedFull-system test unverifiedNo verified construction or operating date
Fort Drum, NYWestinghouse / eVinciInstallation selected; parcel unverifiedApproval unverifiedSite-specific delivery unverifiedZero-power criticality testing reported Aug./Sep. 2026No verified construction or operating date

Sources: [S1]–[S8]. Reactor-family experiments do not establish military installation authorization.

03 / Installation dossiers

Fort Benning, Georgia Radiant • Kaleidos

Configuration: Three planned 1-MWe units. Siting: The October 16 joint assessment inspected a preferred candidate site and examined electrical integration, physical security, emergency response, and environmental and cultural-resource obligations. Final site approval remained conditional as of the reporting cutoff. Fuel: DOE HALEU allocation and TRISO supply arrangements were reported. Testing: Development and demonstration preparations should not be confused with full-power site commissioning. Construction: Not verified. Operating goal: 2028, a vendor target rather than an authorization. [S4] [S8]

Fort Bragg, North Carolina Antares • R1

Configuration: Three units proposed, with reactor-family outputs ranging roughly 100 kWe to 1 MWe. Siting: Base selected; exact parcel approval not verified. Regulatory: No completed site authorization established. Fuel: TRISO supply agreement reported. Testing: Antares Mark-0 achieved zero-power criticality in June 2026; this is a development-system result, not Fort Bragg operation. Construction: Not verified. Operating goal: Initial military deployment targeted for 2028. [S6] [S8]

Fort Campbell, Kentucky BWXT • BANR

Configuration: 20-MWe-class BANR. Siting: Final site selection and characterization in Phase 1. Regulatory: Army nuclear regulatory work being initiated. Fuel: TRISO fabrication included in the work program. Testing: Project Pele supplies related high-temperature-reactor experience, but Pele and BANR are different systems. Construction target: Late 2028. Operating target: Early 2030s, beyond the September 2028 milestone. [S5] [S7]

Fort Hood, Texas General Atomics • GA-TES

Configuration: Approximately 5-MWe baseline, reportedly scalable toward 20 MWe. Siting: Development and site planning announced; parcel approval not verified. Regulatory: Site authorization unverified. Fuel: Uranium-zirconium-hydride technology derived from TRIGA heritage; site-specific fuel fabrication or delivery not verified. Testing: Completed GA-TES full-system nuclear operation not verified. Construction and operating date: Not publicly established in reviewed material. [S1] [S8]

Fort Drum, New York Westinghouse • eVinci

Siting: Installation selected; final parcel approval not verified. Regulatory: Army site-specific authorization not established. Fuel: TRISO-based reference design; no verified Fort Drum-specific fuel delivery. Testing: Cold and high-temperature zero-power criticality experiments in 2026 support reactor-physics validation, not electricity production. Construction and operating date: Not verified. [S1] [S9]

04 / Dated milestone register

  1. Executive Order 14299 establishes the Army-regulated reactor operating objective for September 30, 2028. [S2]

  2. Army announces Janus Program. [S2]

  3. Project Pele TRISO fuel delivery to Idaho National Laboratory reported. [S10]

  4. Antares Mark-0 criticality; BWXT reports Pele core-stacking progress. [S6] [S7]

  5. Army identifies five initial vendor-installation pairings. [S1]

  6. Westinghouse eVinci zero-power criticality experiments reported. [S9]

  7. Fort Benning conducts joint preferred-site assessment with Radiant. [S4]

  8. Army publishes Fort Benning site-assessment report; final site approval remains conditional. [S4]

  9. Outstanding site approval, environmental review, safety authorization, fuel allocation, construction, commissioning and operating authorization. These are gates, not confirmed dates.

  10. Executive-order operating deadline. [S2]

05 / Project Pele: related, not interchangeable

BWXT's Project Pele is a transportable approximately 1.5-MWe high-temperature gas-cooled reactor demonstration for Idaho National Laboratory. Its fuel and manufacturing program informs military microreactor development. It is not the same reactor as the 20-MWe BANR proposed for Fort Campbell. Fuel fabrication, assembly, shipment, authorization, initial criticality and electrical generation must be tracked independently. [S7] [S10]

06 / Outstanding regulatory and deployment gates

The following are verification requirements, not claims that every project uses identical paperwork or approval authorities.

Checkboxes are reader notes only and are not retained when the page closes. No box is pre-checked because none is a universal completed gate across all five installations.

07 / Indexed primary sources and further reading

  1. [S1] U.S. Army, August 26, 2026. Initial Janus agreements, developers and sites. Army announcement ↗
  2. [S2] U.S. Army, October 14, 2025. Janus launch and executive-order context. Army announcement ↗
  3. [S3] U.S. Army, 2025. Nine original candidate installations. Army article ↗
  4. [S4] U.S. Army, October 19, 2026. Fort Benning site assessment. Army article ↗
  5. [S5] BWXT, 2026. Fort Campbell BANR Janus Phase 1. BWXT statement ↗
  6. [S6] U.S. Army, 2026. Antares Mark-0 criticality. Army article ↗
  7. [S7] BWXT. Project Pele program and manufacturing milestones. BWXT project page ↗
  8. [S8] POWER, August 27, 2026. Reactor technology and developer deployment targets. Industry analysis ↗
  9. [S9] U.S. Department of Energy, 2026. Westinghouse eVinci criticality milestone. DOE report ↗
  10. [S10] Idaho National Laboratory, 2025. Project Pele TRISO fuel delivery. INL announcement ↗

Research note: URLs are retained from the source register used in the October 19 assessment. They are provided for independent verification; individual destination availability has not been live-tested in this offline export. Statements marked “reported” or “not verified” should be rechecked before operational or regulatory use.